Finalizing installation - OPT100

OPT100 Installation Guide

Document code
M211857EN
Revision
V
Language
English
Product
OPT100
Document type
User guide
  1. If you have connected DGA monitor to a host system using Ethernet or RS-485 connections, verify the availability of measurement data from the host system.
  2. Verify that you have performed all installation steps according to the configuration report.
  3. Before leaving the installation site, perform a safety check and lock up according to the post-installation checklist.
    Keep the doors closed and locked when not actively working inside the enclosures or accessing the service port locally. Keeping the DGA monitor door closed when performing measurement is important for temperature management of measurement components.
    Figure 1. Turning on DGA monitor with doors closed