All civil works must be completed as instructed in this guide before starting instrument installation. |
The customer is responsible for supplying the accessories, such as grounding cables and conduits for cables. |
Item | Reference | Data | Remarks |
---|---|---|---|
Instrument location | |||
Site is free of obstacles that can disturb the equipment. | Site requirements |
☐ Yes ☐ No |
|
Grounding | |||
System grounding cable ready as instructed. | Grounding |
☐ Yes ☐ No |
|
Grounding resistance tested. Recommended grounding resistance is <3 Ω. | - |
☐ Yes ☐ No |
Measured resistance (Ω): |
Cabling | |||
Cable protection is installed. | Power supply and communication lines |
☐ Yes ☐ No |
|
Data communication cable is ready and tested with a resistance meter. | - |
☐ Yes ☐ No |
|
AC (mains) power supply | - | ||
AC (mains) power is available for the equipment. | Power cabling |
☐ Yes ☐ No |
Measured (V AC, Hz): |
Uninterrupted power supply (UPS) is available for site equipment. | Power supply and communication lines |
☐ Yes ☐ No |
Measured (V AC, Hz): |
Foundation | |||
Foundation bolts are installed and the pattern is verified. | Foundation design and foundation bolt pattern |
☐ Yes ☐ No |