Installing the refractometer - PR53 - PR53AC

PR53AC Installation Guide

Document code
M212866EN
Revision
C
Language
English
Product
PR53
PR53AC
Document type
User guide

Plan the installation location carefully before installation. See Choosing the installation location.

Standard installation:

  • Welding equipment
  • Refractometer
  • Ferrule
  • Gasket
  • Clamp

High pressure installation:

  • Welding equipment
  • 9/16 in wrench (for high pressure clamps)
  • Refractometer
  • Ferrule
  • Gasket
  • Clamp
These are general instructions for the refractometer mounting. Plan the process‑specific installation according to your requirements. Contact Vaisala helpdesk for further assistance if needed.

If you are using a flow cell, see Installing refractometer with flow cell.

  1. Familiarize yourself with the safety instructions of the installation site.
  2. Make sure the process line is depressurized and empty.
  3. Weld the ferrule into the process pipeline.
    For optimal self-cleaning properties, install the refractometer in a 10 Â° downward angle.
    If your system must comply with EHEDG, 3-A or other sanitary standard, see the standard for more detailed welding instructions.
  4. Install the gasket.
    If your system must comply with the EHEDG sanitary standard, use a gasket that complies with the current version of the EHEDG Position Paper.
  5. Mount the refractometer. Make sure the cable glands on the refractometer are in a downward position.
    1. Finger tighten to 3 Nm if you are using the standard clamp (with one tightening screw).
    2. Tighten to 28 Nm with a 9/16 inch wrench if you are using the high pressure clamp (with two tightening screws).
  6. Make sure the refractometer is firmly in place and that there is no excessive vibration. Support the piping if needed.