The transmitter can be installed directly in the process wall through DM240FA duct installation flange. When the transmitter is installed directly on the process wall or pipe, note that a closing valve may be needed on both sides of the installed transmitter so that the sensor head can be removed from the process for calibration or maintenance.
- 1
- Measured gas
- 2
- DMT132 transmitter
- 3
- DM240FA flange (thread G1/2" ISO)
- 4
- Recommended additional hole (plugged) for Td field check reference measurement probe (for example, Vaisala DM70)